工程量计算:
D1:
SC50:15+(0.2+0.3+0.2)=15.7m
VV-3×35+1×16:(2+2+15.7+1)×(1+2.5%)=21.22m
D2:
SC32:12+(0.2+0.3+0.2)=12.7m
VV-3×16+1×10:(2+3+12.7+1)×(1+2.5%)=19.17m
D3:
SC32:13+(0.2+0.3+0.2)=13.7m
VV-3×16+1×10:(2+4+13.7+1)×(1+2.5%)=21.22m
D4:
SC32:0.1+0.2+5+0.2+1.4=6.9m
BV10:(1+2)+6.9+(0.5+0.4)=10.8m
BV16:10.8×3=32.4m
WL1:
PC15:(3-1.4-0.4)+7+8+8=24.2m
BV2.5:[(0.5+0.4)+24.2]×3=75.3m
合计:
SC32:12.7+13.7+6.9=33.3m
SC50:15.7m
PC15:24.2m
VV-3×35+1×16:21.22m
VV-3×16+1×10:19.17+21.22=40.39m
BV16:32.4m
BV10:10.8m
BV2.5:75.3m
注:电缆支架:(0.4×3×1.79+0.8×3.77)×15=77.46
其他综合单价计算过程:
1)照明配电箱:69.66+31.83+69.66×(50%+30%)+2000=2157.22元/台
2)铁构件制作:12.25+1.67+0.57+12.25×(50%+30%)+3.2×1.05=27.65
铁构件安装:7.95+0.32+0.44+7.95×(50%+30%)=15.07
27.65+15.07=42.72元/kg
3)电力电缆:VW-3×16+1×10:7.55+1.12+0.12+7.55×(50%+30%)+52×1.01=67.35元/m
电力电缆VW-3×35+1×16:13.61+1.46+0.66+13.61×(50%+30%)+138×1.01=166.00元/m
4)电缆终端头16mm^2:59.08+98.62+59.08×(50%+30%)=204.96元/个
5)电缆终端头35mm^2:96.68+143.56+96.68×(50%+30%)=317.58元/个
6)钢管暗配Φ32:[785.70 + 144.94 + 41.50+785.70×(50% +30%) ]×0.01+9.30×1.03=25.59元/m
7)钢管暗配Φ50:[1341.60+248.40+59.36+1341.60×(50%+30%)]×0.01+12.80×1.03=40.41元/m
8)管内穿线BV-2.5:[79.99+44.53+79.99×(50%+30%)]×0.01+2.20×1.16=4.44元/m
9)管内穿线BV-10:[73.00+48.00+73.00×(50%+30%)]×0.01+7.92×1.05=10.11元/m
10)管内穿线BV-16:[85.00+48.00+85.00×(50%+30%)]×0.01+13.80×1.05=16.50元/m
11)工厂罩灯:[158.60+49.00+158.60×(50%+30%)]×0.1+150×1.01=184.95元/套
12)接线盒:[36.00+53.85+36.00×(50%+30%)]×0.1+2.70×1.02=14.62元/个
13)低压交流异步电动机(13KW以下):230.40+65.98+16.76+230.40×(50%+30%)=497.46元/台
14)低压交流异步电动机(30KW以下):360.90+88.22+22.44+360.90×(50%+30%)=760.28元/台